LAX's SkyLink Train Sinks Deeper Into Junk-Bond Territory Ahead of a Dec. 8 Deadline It Is Almost Sure to Miss
Fitch cut $1.2 billion in people mover bonds to B-, warning that a missed deadline could open the door to terminating the contract, as testing keeps restarting and the contractor now targets February at the earliest.

WESTCHESTER — The driverless trains are running the full 2.25-mile route above Los Angeles International Airport, but only as tests, and the money behind them is running out of patience. With a Dec. 8 deadline three weeks away, the $1.2 billion in bonds that financed LAX's SkyLink people mover have been pushed deeper into junk territory, and the people who rate that debt now say a missed deadline is all but certain.
Fitch Ratings cut the project's senior revenue bonds to B- from BB, a four-notch drop since July, the Los Angeles Times reported. The downgrade "reflects the near certainty" that the contractor, LINXS, won't have the train running by Dec. 8, leading to a "technical event of default" that could let either LINXS or Los Angeles World Airports issue project termination notices, Fitch said in its rating action, which also kept the bonds on Rating Watch Negative.
"It's an uncommon action of severity," Fitch analyst Seth Lehman told the Times. "We were under the view that there was a fair amount of cushion for LAWA and LINXS to settle on disputes, or for LINXS to show that they can have the trains run safely per this reliability test."
Why Dec. 8 Matters
LINXS, short for LAX Integrated Express Solutions, is a consortium that includes Fluor, Balfour Beatty, Alstom Transport USA, ACS Infrastructure Development and HNTB. It built the train under a public-private partnership and is paid by the airport once the system is available to passengers. Bondholders had earlier agreed to push the key deadline from Oct. 8 to Dec. 8, and Fitch estimates LINXS's remaining cash will be used up by mid-2027, Rail and Runway reported.
Missing the date does not end the contract on its own. Lehman told the Times there is a 120-day buffer to settle issues afterward. "After you get past that date, then the question becomes: Will both sides still want to work with each other, or just decide to find a path toward separation?" he said.
The contractor is already paying for the delay. Because LINXS missed its contractual completion deadline in December 2025, it is losing $8.3 million a month in availability payments and has lost more than $85 million so far, the airport said in a SkyLink fact sheet dated Nov. 3. If the train isn't ready for passengers by Dec. 8, the fact sheet says, LINXS's bondholders have "a range of remedies at their disposal."
Testing Keeps Restarting
Officials describe the project as 99% complete. But before anyone can ride, the system must run 30 consecutive days of testing without substantial problems and win sign-off from the airport and an outside assessor, and that clock has repeatedly reset. In late September, four arc blasts damaged the power rail and guide beam during testing, Engineering News-Record reported. Repairs have been made and testing has resumed, but LINXS has not yet identified a root cause.
LINXS's latest monthly report targets passenger service no earlier than Feb. 5, 2027, a month later than its previous estimate, and warned the delay would grow day for day until the airport and the Department of Water and Power sign an agreement on solar power for the train, Angeleno Daily reported, citing the Times. The airport has not confirmed any date and says it will announce an opening only once testing is complete.
The two sides have been fighting for months. In July, LINXS sued the city over a disputed $115 million payment, blaming the airport for delays and design changes, according to ENR. Meetings among top executives stopped in August, the Times reported. In a statement to the paper, the airport said it would not comment on "private financing arrangements, lender discussions, contractual milestones, or rating agency decisions" but is "working with LINXS around the clock" while "exercising available remedies within the contract to hold them accountable." LINXS said it "remains committed to working with LAWA to successfully deliver the Automated People Mover."
A $3.3 Billion Centerpiece
The train is the most anticipated piece of the airport's $30 billion overhaul. Construction began in 2019 on a project first estimated at $1.9 billion, according to ENR; it now costs $3.3 billion, is three years behind schedule and was meant to open in 2023, well ahead of the 2028 Olympics. When it opens, the fare-free line's six stations will link the terminals with parking, a consolidated rental car center, a new ride-hail lot and Metro's LAX/Metro Transit Center, replacing about 3,200 daily shuttle trips.
The delays became an issue in the mayor's race. Mayor Karen Bass, who noted the project predates her administration, said in late October that she expected the train to be running "by the first of the year because if it's not, then one of the contractors is going to face severe financial penalties," NBC Los Angeles reported. Nithya Raman, who has since won the race, said during the campaign that her first-week priority would be convening airport, DWP and contractor officials to break the logjam.
"Each time there's a path towards opening, there's a setback," Lehman told the Times.
More Business

Speakpreneur Founder Paul Getter On A Mission To Help Entrepreneurs

L.A. office leasing hits highest level since 2019

L.A. industrial vacancy falls for first time in two years

Naples Speaking Coach Bets Entrepreneurs' Next Growth Channel Is the Stage

1,500 Founders Gather in Dallas as HighLevel Opens LevelUp 2026
Trending
- 1L.A. switches on first speed cameras in citywide crackdown on fast drivers
- 2SoCal coast braces for possible record-high tides through Thursday
- 3Bass calls for independent audit of LADWP as utility bills spike
- 4Bass and Raman clash over small business as the Valley becomes a battleground
- 5Key vote set on who runs L.A.'s homelessness data and housing-matching systems
- 6City Council delays LAPD plate-reader pilot, OKs DASH bus-lane cameras
- 7$22 million in state money headed to the Sepulveda Basin
- 8Suspected DUI driver kills 2 cyclists on pre-Halloween group ride in Montclair
Latest
- Vernon, L.A.'s Last Haven for Data Centers, Weighs Environmental Review as LAUSD Fights a Project Next to a SchoolNov. 13, 2026, 11:30 AM ET
- Camp Flog Gnaw Returns to Dodger Stadium This Weekend, and the Rain Should Be Gone by the Time the Gates OpenNov. 13, 2026, 2:30 PM ET
- UCLA Goes for a Record-Tying 10th Win Tonight at the Rose Bowl as the Clippers Host the Thunder and Reaves Is Day-to-DayNov. 13, 2026, 5:30 PM ET
- Storm Drops Up to 2 Inches in L.A.'s Mountains as Big Surf Peaks Saturday and More Rain Lines Up for Next WeekNov. 14, 2026, 8:00 AM ET
- Ugarte Leads by 41 Votes in L.A.'s Council District 9 Race as a Ballot Complaint Goes to the D.A.Nov. 14, 2026, 11:30 AM ET
- Sheryl Crow Headlines Tonight's Free 'Live On Sunset' Concert as the Sunset Strip Closes to CarsNov. 14, 2026, 2:30 PM ET
- UCLA Is 10-0 and Tied for the School Record as the Clippers Stun the Thunder and the Kings Host Calgary Without PanarinNov. 14, 2026, 5:30 PM ET
- LAX's SkyLink Train Sinks Deeper Into Junk-Bond Territory Ahead of a Dec. 8 Deadline It Is Almost Sure to MissNov. 15, 2026, 8:30 AM ET
- L.A. County's Regional Parks Lost an Estimated 150,000 Visitors After the 2025 Immigration Raids, and Families Still Haven't ReturnedNov. 15, 2026, 11:30 AM ET
- Space Shuttle Endeavour Is Back on View, Standing Upright, as L.A.'s New Air and Space Center Wraps Its Opening WeekendNov. 15, 2026, 2:30 PM ET